Questions
ayuda
option
My Daypo

ERASED TEST, YOU MAY BE INTERESTED ONShe's so LUCKY, she's a star

COMMENTS STATISTICS RECORDS
TAKE THE TEST
Title of test:
She's so LUCKY, she's a star

Description:
The only way is up

Author:
Max
(Other tests from this author)

Creation Date:
06/02/2024

Category:
Others

Number of questions: 21
Share the Test:
Facebook
Twitter
Whatsapp
Share the Test:
Facebook
Twitter
Whatsapp
Last comments
No comments about this test.
Content:
Which of the following MRP elements can be created for a material procured externally by a requirements planning run? (2 answers) Production order Scheduling agreement schedule lines Sales order Purchase requisitions Purchase order Outline agreement.
Which of the following factors influence the type of procurement proposals that are created by the MRP run? (2 answers) The procurement type of a material The MRP procedure of a material The plant parameters The method to run MRP.
In demand driven planning, planned requirement quantities trigger requirements calculation? True False.
Consumption based planning methods are usually based only on past material usage? True False.
In forecast based planning, you can consider external requirements? True False.
MRP areas can only be specified within a plant? True False.
How many subcontractors can be included in a subcontractor type MRP area? (1 answer) 0 1 2 3 Unlimited.
Receipt elements (planned orders, purchase requisitions) containing a storage location that belongs to an MRP area are assigned to this MRP area automatically? True False.
Select the possible types of MRP area for planning (3 answers) Company code Plant Warehouse Storage location Subcontractor.
Which field in the material master record controls whether a material is planned consumption based or demand based? The MRP profile The MRP type The MRP group The MRP controller.
On which organizational levels can MRP relevant fields like lot-sizing procedure or MRP type be maintained in a material master record? (2 answers) Plant Storage location MRP area Client.
Which of the following statements apply to the MRP type? (2 answers) The MRP type is assigned to a material and controls the MRP procedure A material can have different MRP types per plant and even per MRP area The MRP types are delivered by SAP and cannot be changed Allowed MRP types are defined per material type.
What are the lot sizing procedures categories? (3 answers) Static Periodic Exact Optimizing Dynamic.
The replenishment lead time of a material is the sum of the purchasing department processing time, planned delivery time and goods receipt processing time. These three elements can be maintained in the material master record. True False.
The following describes the individual sub-processes of a planning run: Check the planning file, net requirements calculation, lot-size calculation, scheduling, and type of procurement proposal determination. With the corresponding settings, the system determines a source of supply during a planning run for externally procured materials, and assigns them directly to the procurement proposal. True False.
The low level code is the lowest level at which a material appears within a bill of material (BOM) True False.
The low level code that is used during the MRP run is automatically determined and is displayed in the planning file True False.
In the reorder point planning MRP procedures, procurement is triggered when the sum of plant stock and fixed receipts falls short of the reorder point. The reorder point should include the expected average material requirements during the replenishment lead time, plus a safely stock to safeguard against uncertainties. True False.
During net requirements calculation of a material planned with reorder point planning, the warehouse stock available for MRP includes the plant stock and the on-order stock. Which of the following elements belong to on-order stock? (3 answers) Purchase requisitions Purchase orders Sales orders Firm planned orders Fixed purchase requisitions Planned orders.
During backward scheduling for a material planned with reorder point planning, the system defines the date on which the material will be available, starting from the date of the planning run. Starting with today’s date, the availability date is calculated by adding the purchasing department processing time (in working days), the planned delivery time (in calendar days), and the GR processing time (in working days). True False.
The MRP group is assigned to the relevant master record according to the material type True False.