Subject to which prerequisites can a source of supply be assigned as early as during the MRP run? The 'MRP-relevant' indicator must have been set in a contract item. The source determination facility must be activated at the start of the MRP run. A quota arrangement must exist and the quota arrangement usage indicator must allow use of the quota arrangement in materials planning. An info record must exist for the relevant material and the vendor must have been flagged in the source list as the single/sole source of supply for the purposes of materials planning.
What is the purpose of specifying a planning horizon? Only materials manifesting a planning-relevant change within the planning horizon are taken into account in the MRP run (where NETPL is used). To specify whether forecasts are included in the material requirement calculation. To specify that only externally procured (and not internally procured) items are included in the net change MRP run. To specify whether a NETCH (net change in complete horizon) or a NETPL (net change in planning horizon) will take place in the next MRP run.
In which sequence are materials taken into account in the planning run in the case of total planning? By low-level code in ascending order. By material group in ascending order By the number of days since the last planning run in descending order. By material number in ascending order.
Which time intervals does the replenishment lead time include? Purchasing department processing time in Customizing. Planned delivery time in the material master record. Goods receipt processing time in the material master record. Goods receipt processing time in the plant parameters. Requirement lead time in the material master record.
Which transaction shows the most up to date planning data? Stock Requirement list MRP list Stock Overview report List display of material and accounting documents.
To view the most up to date planning data (available stock, orders, reservations, etc) on a material,use the Stock Requirement list. Stock Overview report List display of material and accounting documents MRP list Standard Analysis for a material.
In which of the following MRP types can be used forecast? Automatic reorder point planning Forecast based planning Time phased planning Manual Reorder point planning Storage location MRP.
A material forecast can be used by the following MRP types: Automatic reorder point planning Forecast based planning Time phased planning Manual Reorder point planning Storage location MRP .
Which are the groups of procedures for calculating the lot size? Static lot sizing procedures Periodic lot-sizing procedures Optimizing lot-sizing procedures Fixed order quantity .
The following are lot sizing rules available for SAP R/3 Fixed lot size Replenish to maximum stock level Weekly lot size Daily lot size Economic order quantity.
Which is the use for the MRP groups? Organizational object used to allocate certain control parameters for MRP to a group of materials Organizational object used to allocate certain control parameters for MRP to a group of MRP types Organizational object used to allocate certain control parameters for MRP to a lot size procedures.
Which of the following statements regarding safety stock are true? A change in the safety stock level leads to a planning file entry. Safety stock serves to bridge delays in delivery. Stock can never fall below the safety stock level. The safety stock is used to cover both any unplanned excess material consumption and the requirement with delivery delays Safety stock can be calculated automatically in configuration in the MRP type The quantity of the safety stock must be lower than the reorder point The following values must be considered when specifying the reorder point: Safety stock, previous consumption or future requeriment, replenishment lead time Safety stock raises the reorder point. In reorder point planning, safety stock is a constituent part of the reorder point (stock level at which reordering takes place.
Materials planning can be set to automatically generate Planned Orders Purchase Requisitions Contracts Purchase Orders Delivery Schedules.
Which of the following are mandatory entries enabling requirements planning to be carried out for a material? Requirement planning must be activated for the plant concerned You must specify that this material is subject to planning via the MRP type in the material master record A reorder point must be defined in the material master record A valid source of supply must exist for the material.
Which elements belong to MRP-available stock? Warehouse stock Purchase order Fixed purchase requisitions Fixed reservations Planned orders Fixed.
Avaliable stock element in MRP Warehuose stock Purchase order Fixed plan order Fixed purchase requisitions.
Which of the following MRP areas do not exist? Consignment MRP area Plant MRP area Storage location MRP area Subcontractor MRP area .
which procurement elements can you directly convert a planned order? Purchase requisition Production order Purchase order Contract.
External requirements in reorder point procedure External requirement are not included in reorder point planning as MRP-relevant changes in the total horizon or the planning horizon We include external requeriment JUST if we change the configuration field include ext. reqmts in the MRP type.