option
Questions
ayuda
daypo
search.php
ERASED TEST, YOU MAY BE INTERESTED ON C_TPLM22_67 SAP PROJECT SYSTEMS WITH SAP ERP 6.0 EHP 7.0
COMMENTS STATISTICS RECORDS
TAKE THE TEST
Title of test:
C_TPLM22_67 SAP PROJECT SYSTEMS WITH SAP ERP 6.0 EHP 7.0

Description:
SAP PROJECT SYSTEMS WITH SAP ERP 6.0 EHP 7.0

Author:
sj.agarwal0127@gmail.com
Other tests from this author

Creation Date:
03/10/2020

Category: Others

Number of questions: 10
Share the Test:
New CommentNuevo Comentario
No comments about this test.
Content:
You plan to work with network and WBS elements structures: What do you have to consider? You can assign a network header to multiple WBS elements You have to activate the operative indicator "Account assignment element" for WBS elements with activities. You have to maintain a network profile in the project profile You can reassign an activity from one network to another.
You intend to work with predefined project coding masks to create project definitions. What do you have to consider? The standard project definition must differ from the definition of the operative project. You can create a project coding mask X even if there are project numbers beginning with X You can use only number for a project coding mask definition You can use an indicator to determine that only coded project numbers may be used within the Project System.
The system status of a WBS element is created (CRTD). No status profile is assigned to this WBS element. Which business process is allowed for this WBS elements? Goods receipt for purchase orders Creation of purchase orders Calculation of actual values Activity allocation.
Where do you control whether a project stock is managed as valuated or non-valuated project stock? In the material master In the WBS element In the network activity In the project definition.
In your project, you work a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario? The purchase order can be updated in Goods Receipt Purchase Order (MIGO) The purchase order is updated automatically to match the purchase requisition white saving the project A workflow can be triggered to inform the purchasing group. No system support is required, since the purchase order and the purchase requisition are always split.
You want to create a purchase requisition for the materials used in you project. However, after releasing the project no purchase requisition has been created. What could be the reason? (2) The item category of the material is set to Non-Stock item The procurement type in the material master is set to in-house production The item category of the material is set to Stock item The materials have no material number.
Which sales documents can update planned revenues on WBS elements? (2) Sales order Quotation Billing Inquiry.
How can you define external tasks in your project ? (2) Assign a purchase order for external processing to the project definition Create a service activity in a network Create an external activity in a network Create a service milestone.
How can you update the degree of processing for an activity? By using results analysis By charging the activity By scheduling the activity By confirming the activity.
How can the system activate requirements (such as reservations or purchase requisitions)? (2) When releasing a network or an activity Immediately, by saving the project Automatically, using the requirement date and the replenishment lead time Using a standard milestone activity.